Kavango Resources said on Monday its pilot gold plant in Zimbabwe had been declared operational by the mines ministry, a step it says moves its Hillside project closer to commercial-scale production.
BY BUSINESS REPORTER
The ministry’s Matabeleland South office certified the 50-tonne-per-day plant and its tailings storage facility on October 30 after reviewing documents and inspecting the site in the week of October 26, the company said. Both met mining, safety and environmental requirements, it said.
The plant is small and built as a proof of concept. It produced 539 grammes of gold in September, up from 397 grammes at the first elution in August, and is meant to generate data to guide the design of a larger facility, the company said.
“The concept phase plant enables us to optimise processing performance, confirm metallurgical recoveries under operating conditions and further refine our understanding of the orebody ahead of larger-scale development,” chief executive Jasper Musadaidzwa said.
Kavango expects gold recoveries of 90% to 93% under commercial conditions. Laboratory tests on blended ore from the Nightshift and Bill’s Luck deposits achieved recoveries above 95%, it said in May.
Bill’s Luck Underground hosts a JORC-compliant resource of 33 900 ounces of gold, across the measured, indicated and inferred categories, at a grade of 2,68 grammes per tonne.
Kavango said it is installing a 13-metre headframe at the Bill’s Luck main vertical shaft and upgrading power, water and accommodation infrastructure as it prepares for larger-scale production.