Zimbabwe could get its first utility-scale wind farm by 2029 under a US$300 million wind, solar and battery project planned by Tatanga Energy and Modaso Energy, the energy unit of Swiss-based MISA Group, the developers said on Tuesday.
BY BUSINESS REPORTER
The Guruve-Mazowe (Chikonyora) plant in Mashonaland Central would supply about 5% of current national generation from a source that does not depend on rainfall. However, it still needs a power purchase agreement with state utility Zesa, now under negotiation, before financial close targeted for mid-2027.
The project would combine 128 megawatts (MW) of wind, 100 MWac of solar and a 50 MW/100 MWh battery behind a single 100 MW grid connection. It is expected to generate about 550 gigawatt-hours a year.
Standard Bank has been appointed lead arranger for the project debt, and a term sheet has been agreed. Construction would start immediately after financial close, with commercial operation targeted for 2029.
OFFTAKE
Zesa is set to be the main buyer, but talks on the power purchase agreement and a use-of-system agreement are still under way.
“This will be Zimbabwe’s first utility-scale wind farm, and our country’s first project to combine wind, solar and battery storage. It means new clean power for Zimbabwe, and new skills for Zimbabweans. We are proud to help build it,” said Cletus Nyachowe, Zesa’s group chief executive.
Africa GreenCo, through its Zimbabwean unit ZimGreenCo, has signed heads of terms to buy a share of the output under a long-term contract. Surplus power may be sold into the Southern African Power Pool.
“ZimGreenCo gives Guruve-Mazowe a second route to market alongside Zesa,” said Lion Mashiri, Africa GreenCo’s managing director for Zimbabwe. “That diversified revenue makes the project stronger for lenders and helps bring private investment into Zimbabwe’s power sector.”
Zimbabwe has struggled with power shortages linked to low water levels at the Kariba hydropower plant. The developers said the plant’s output would not depend on rainfall, Kariba levels or imported fuel.
BENEFITS
The companies said the project would create about 1 000 construction jobs, avoid about 0,5 million tonnes of carbon dioxide a year and require no resettlement. They said it would account for about 11% of Zimbabwe’s target of 2 100 MW of renewable capacity by 2030.
Tatanga originated the project and has led land, community and permitting work since a wind measurement campaign began in 2021. Modaso redesigned it from a wind-only scheme into a hybrid.
“There is no shortage of renewable resources in Africa; but there is a shortage of electrons at the right place and the right time,” said Guy Hacking, chief executive of MISA Group.