KAVANGO Resources has increased power capacity at its Hillside Gold Project in Zimbabwe fivefold by installing a new transformer, strengthening the infrastructure needed to expand gold processing and advance its production ambitions.
The 1 megavolt-ampere (MVA) transformer, energised on November 19, raises the project’s total installed electricity capacity to 1.25 MVA from 250 kilovolt-amperes (kVA).
The upgrade marks another step in Kavango’s efforts to move Hillside towards more efficient gold production, with reliable grid electricity expected to support underground operations and the site’s proof-of-concept carbon-in-leach (CIL) processing plant. The company also expects the improved power supply to reduce operating costs and provide greater energy stability.
The London- and Victoria Falls-listed exploration company said the new transformer would supply electricity directly from the national grid to the project.
Hillside also has 500 kVA of backup generation capacity to maintain operations during grid interruptions.
“Reliable, cost-effective power is fundamental to building an efficient gold production operation,” chief executive Jasper Musadaidzwa said in a statement.
The development comes amid improving electricity supply conditions in Zimbabwe.
The company cited comments by the Energy minister in Parliament on November 10 that the country had gone 325 consecutive days without load shedding caused by insufficient power generation.
The power upgrade follows the commissioning of Kavango’s 50-tonne-per-day gold processing plant, announced on November 2.
The company said it would continue strengthening site infrastructure to support increased processing capacity.
However, Kavango did not disclose the cost of the transformer upgrade or provide a timeline for expanding processing operations.